Arbitration — pre-award and post-award interest

Citation: 2026 INSC 1135Decision: Supreme Court of India
On this page

Decision in brief

The arbitrator awarded pre-reference and pendente lite interest despite a contractual prohibition. The Supreme Court upheld the limited interference removing that interest, while retaining the substantive award and post-award interest. Section 31(7)(a) makes the pre-award power subject to the parties’ agreement.

Why it matters for exams

Keep the two statutory periods distinct. Under the judgment’s analysis, the contractual bar governing pre-award interest did not remove the statutory post-award entitlement under Section 31(7)(b). Identify the period, contractual clause and applicable statutory provision before concluding whether an interest award exceeds the tribunal’s authority.

Source and case reference

Sharma Enterprises v. National Building Construction Corporation · 2026 INSC 1135 · Supreme Court of India · 2026-10-15. This study explanation is prepared by Target for IQ. Read the holding together with the facts and procedural stage described above.

Related Post

00 Comment 5 days ago

Dharmvir Rai Vs The State of Bihar | BRHC010586272026

TARGET FOR IQ · HIGH COURT DOCUMENT LIBRARYDharmvir Rai Vs The State of Bihar2026-07-15 · Patna High Court · OrderCase at a glanceDharmvir Rai Vs The State of Bihar is indexed as...

00 Comment 5 days ago

Meera Kumari Vs The State of Bihar | BRHC011207812024

TARGET FOR IQ · HIGH COURT DOCUMENT LIBRARYMeera Kumari Vs The State of Bihar2026-07-31 · Patna High Court · OrderCase at a glanceMeera Kumari Vs The State of Bihar is indexed as...