Case at a glance

MD. MOAZZAM Vs THE STATE OF JHARKHAND THROUGH THE DEPUTY COMMISSIONER, HAZARIBAG is indexed as an order of the High Court of Jharkhand dated 2026-09-30. The court-issued text is reproduced below with its original page boundaries, followed by a downloadable source PDF.

CourtHigh Court of Jharkhand
Decision date2026-09-30
Document typeOrder
Case titleWPC/7574/2026 of MD. MOAZZAM Vs THE STATE OF JHARKHAND THROUGH THE DEPUTY COMMISSIONER, HAZARIBAG
Case reference (CNR)JHHC010326132026

How to read this decision

Start with the parties and the procedural history, identify the relief sought, and then read the court’s reasoning together with its final directions. Submissions made by a party are not automatically findings of the court. A direction made in this proceeding should be read in its factual and procedural context.

This page provides the court document and case metadata. It does not assign an unverified holding, outcome, or precedential rule. For exact wording, citations and formatting, use the original PDF; searchable text extraction can change line breaks and spacing.

Download the court PDF

Searchable court text

Source page 1

Neutral Citation No. (2026:JHHC:29377)

IN THE HIGH COURT OF JHARKHAND AT RANCHI W.P.(C) No.7574 of 2026 —– 1. Md. Moazzam, son of Late Ghulam Rasul.

2. Md. Arsad, son of Late Ghulam Rasul. 3. Aliza Warsi, daughter of Md. Moazzam.

All are residents of village-Chattibariyatu, P.O.- Chattibariyatu, P.S. Keredari, District-Hazaribagh, Jharkhand.

………. Petitioners. -Versus- 1. The State of Jharkhand through the Deputy Commissioner, Hazaribag. 2. The Managing Director, NTPC Limited, having its office at Ginni Plaza, in front of Chutia Police Station, Station Road, Chutia, Ranchi. 3. The General Manager, NTPC Limited, having its office at Sikri Site, Barkagaon, Hazaribagh. 4. The Additional General Manager (H&R), NTPC Limited, having its office at Sikri Site, Barkagaon, Hazaribagh.

5. The District Land Acquisition Officer, Hazaribag. 6. The Circle Officer, Keredari, Hazaribag.

………. Respondents. —– CORAM : HON’BLE MR. JUSTICE RAJESH SHANKAR —– For the Petitioners : Mr. Suraj Prakash, Advocate For the State : Mr. Deepak Kr., A.C. to S.C. (L&C)-III For the NTPC : Mr. Prashant Pallav, A.S.G.I. Mr. Shivam Kr. Parashar, A.C. to A.S.G.I. —– Order No.03 Date: 30.09.2026

1. The present writ petition has been filed seeking issuance of an appropriate direction upon the respondents to make payment of the Rehabilitation and Resettlement (R&R) Grant to the petitioners with effect from the cut-off date, i.e., 25th April, 2022, along with interest thereon at the rate of 18% per Page 1 of 4

Source page 2

Neutral Citation No. (2026:JHHC:29377) annum. The petitioners have also sought payment of compensation in respect of House No. CB-694.

2. Heard learned counsel for the parties and perused the contents of the writ petition.

3. Learned counsel appearing for the petitioners, in course of argument, refers to the letter dated 24th April, 2026 (Annexure- 6/1 to the writ petition), issued by the Central Public Information Officer, National Thermal Power Corporation Limited (in short, ‘NTPC Ltd.’), to Md. Moazzam, petitioner no.

1 herein. It is submitted that, as per the information furnished under the provisions of the Right to Information Act, 2005 (in short ‘RTI Act’), petitioner nos. 1 and 2 have been found eligible for payment of the R&R Grant, whereas the claims of the other family members are yet to be finalized for want of complete documents.

4. It is further submitted that, despite petitioner nos. 1 and 2 having been found eligible for payment of the R&R Grant, the same has not been given to them. So far as the claims of the other family members are concerned, learned counsel submits that, as per his instruction, all relevant documents have already been submitted before the competent authority. It is, however, submitted that if any further document is required, the competent authority of NTPC Ltd. shall intimate the same to the concerned family members, who shall, upon receiving such intimation, furnish the requisite documents before the competent authority.

Page 2 of 4

Source page 3

Neutral Citation No. (2026:JHHC:29377)

5. It appears from a perusal of the information furnished by the Central Public Information Officer, NTPC Ltd., to petitioner no.

1 vide letter dated 24th June, 2026, that petitioner nos. 1 and 2 have been found eligible for payment of R&R Grant.

However, according to the petitioners, they have not been given the said payment by the respondent-NTPC. Moreover, the claims of other family members are still pending for want of certain documents.

6. In view of the aforesaid circumstances, respondent no. 3 or any other competent authority of NTPC Ltd. is directed to take up the matter on priority and to make payment of (R&R) Grant in favour of petitioner nos. 1 and 2, since they have been found eligible for the same, as is evident from the information furnished under the RTI Act, vide letter dated 24th April, 2026.

7. So far as the claims of the other family members, including petitioner no. 3, are concerned, respondent no. 3 or any other competent authority of NTPC Ltd. shall communicate them to furnish the requisite documents so as to finalize their claims with respect to R&R Grant. Upon receipt of the said communication, petitioner no. 3 and/or other family member shall submit the requisite documents within three weeks from the date of receipt of such communication. Thereafter, respondent no. 3 or any other competent authority of NTPC Ltd. shall take an informed decision with respect to their claims for payment of the R&R Grant within three weeks thereafter.

Page 3 of 4

Source page 4

Neutral Citation No. (2026:JHHC:29377) The said exercise shall be completed within eight weeks from the date of receipt/production of a copy of this order.

8. The writ petition is disposed of with aforesaid direction.

9. I.A. No.13851 of 2026 also stands disposed of.

(Rajesh Shankar, J.) Rohit/ 30.09.2026 Uploaded on 30.09.2026 Page 4 of 4

Source and document details

Source: court-issued document indexed through eCourts and distributed in the Indian High Court Judgments open-data collection by Dattam Labs, under CC BY 4.0. Text extraction, layout, navigation and study guidance were added by Target for IQ. No court or data-publisher endorsement is implied.

Original file: JHHC010326132026_1_2026-09-30.pdf. Download the source PDF from this website.

Search all legal current affairs

Related Post

00 Comment 5 days ago

Dharmvir Rai Vs The State of Bihar | BRHC010586272026

TARGET FOR IQ · HIGH COURT DOCUMENT LIBRARYDharmvir Rai Vs The State of Bihar2026-07-15 · Patna High Court · OrderCase at a glanceDharmvir Rai Vs The State of Bihar is indexed as...

00 Comment 5 days ago

Meera Kumari Vs The State of Bihar | BRHC011207812024

TARGET FOR IQ · HIGH COURT DOCUMENT LIBRARYMeera Kumari Vs The State of Bihar2026-07-31 · Patna High Court · OrderCase at a glanceMeera Kumari Vs The State of Bihar is indexed as...