CA Ramchandra Dallaram Choudhary v. Adani Infrastructure and Developers Pvt. Ltd.
Case study notes · 2 min read · English
Insolvency law · Appeal limitation and refiling defects
On this page
Decision in brief
The Supreme Court dismissed the defective appeal as time-barred. It emphasised the forty-five-day filing period and the limited additional fifteen days available on sufficient cause. The judgment also addressed the twenty-eight-day period for curing notified defects under the applicable framework. Previous relief concerning refiling before the NCLAT was confined to that stage and did not create an entitlement to repeated condonation. Independently, the explanations offered did not establish sufficient cause.
Background
An insolvency appeal reached the Supreme Court after delays in filing and curing defects. The appellant relied in part on earlier indulgence granted during a previous appellate stage of the same litigation.
Legal question
Could an earlier condonation justify further relaxation despite the strict timetable governing a Section 62 IBC appeal?
Why it matters for exams
Separate delay in initially invoking jurisdiction from delay in correcting an otherwise timely filing. Do not assume a general equitable power can override an express statutory outer limit. Insolvency procedure prioritises expedition and finality, while each request for condonation must be assessed under the provision governing that particular forum and stage.
Source and case reference
CA Ramchandra Dallaram Choudhary v. Adani Infrastructure and Developers Pvt. Ltd. · Supreme Court of India, judgment dated 1 June 2026 · Supreme Court of India · 2026-06-01. This study explanation is prepared by Target for IQ. Read the holding together with the facts and procedural stage described above.